The Full Project Timeline Explained
Understanding why the total timeline is 6–10 weeks even though construction only takes a week:
Week 1: Free consultation and estimate
We visit your property, discuss design and materials, take measurements. You receive a written fixed-price quote within 3 business days.
Weeks 1–2: Contract and permit application
Once you sign the contract, we apply for permits immediately. In Seattle, permit applications require construction drawings that we prepare.
Weeks 2–8: Permit processing
This is the variable that most contractors don't tell you about upfront. Seattle's permit office processes residential decks in 2–6 weeks. Bellevue and Redmond are faster (1–3 weeks). We track your permit status and notify you when it's approved.
Weeks 6–10: Construction
Once the permit is in hand, we schedule your build. Most residential decks take 3–7 construction days. We crew each job appropriately to complete efficiently.
Final: Inspections
Seattle requires a framing inspection (during construction) and a final inspection. We schedule both with the city and you're welcome to be present.